Hi,
After the clocks changed to summer time last Sunday, the chores in Arc did not take this into consideration.
The chore shown in the screenshot effectively runs at 10:15 and not at the displayed Start Time of 09:15 which is correct as CEST is equal to UTC +2 now.
Before the switch to summer time the chore was scheduled for 09:15 UTC to start at 10:15 CET. After the switch the chore started at 11:15 CET, so I had to reschedule it to 08:15 UTC for it to start at the desired time of 10:15 CEST.
Anyone else with a similar experience?
Arc version is 5.2.1
Alex